- Home
- Dhamile Khola
A dedicated technical centre of MHP
For the development of micro hydropower sector, NMHDA had contributed significantly by producing trained manpower as MHP Operators. The village based working people are thus provided with skill and knowledge on operating MH plants. Advanced level trainings are conducted for experienced MHP Operators to properly maintain and repairing of wear and tear parts of electro-mechanical equipment and civil structures. Engineers, overseers and technicians are also trained in NMHDA training programmes. Such programmes are aimed to impart skills and knowledge to make them Surveyors, Designers, Installers, Trouble shooters, Power Output Verification Inspectors. Thus, human resource development has been one of the successful activities of NMHDA. Since 1996, NMHDA has conducted MHP Operators training programmes 57 times so far 9till April 2016)
Keeping in view the requirement of a live site with all facilities for human resource development and effective demonstrations to trainees and students, NMHDA has conceptualized the Model MHP and initiated construction works of a Model MHP at Ward No.8, Setidevi VDC, Pharping, Kathmandu (now Dakshinkali Municipality, Ward No. 5). The location of the project is quite near to the Pharping Powerhouse, Nepal’s first hydropower project established in 1911. The Model MHP lies at 10 +2 km from Ring Road at Balkhu, Kathmandu.
Water from two different sources is to utilize to run two different units of turbines in the same powerhouse; one is Dhamile Khola which is to utilize for a Pelton turbine and will generate 37 kW and other is Simaldhara Khola which is to utilize for a Cross-flow turbine and will generate 10 kW power. According to support proposed by a prestigious institution for installing a Francis turbine to house in the same Powerhouse, necessary planning has been added.
Some technical features of the Model MHP are given below in tabular form.
Technical Description | Dhamile Khola (37 kW) | Simaldhara Khola (10 kW) |
Designed discharge | 86 LPS & 43 LPS | 35 LPS & 18 LPS |
Gross Head | 73 m | 54 m |
Design capacity | 37 kW (wet) and 18 kW (dry) | 10 kW (wet) and 5 kW (dry) |
Headrace Canal | 317.5 m stone masonry | 30 m stone masonry |
Penstock Pipe | 187 m with 250 mm Dia. | 75.5 m, 180 mm Dia. HDPE pipe and 85 m, 165 Dia. MS pipe |
Turbine type | Pelton Turbine | Cross-flow Turbine |
Driving system | Belt drive system | Belt drive system |
Generator Type | 75 kVA, 3 phase, Brushless Synchronous | 20 kVA, 3-phase, Brushless, Synchronous |
As a Model and Demonstration Site the project have following features
However, much attention is paid to make it a suitable place for studies as well as for Research and Development in micro/mini hydropower technology and its application for the broader benefit of people living in remote area.
Consultant of Survey and Design, estimate that a sum NRs. 11 million approximately will be required to complete constructions of Dhamile Khola Model MHP. Then NMHDA decided to construct the Model project in support of different institutions and NMHDA member companies. In this regard, some of the supports have been already availed in form of cash and kind from different institutions and member companies which are shown below;
S.No. | Institution/Company/Firm | Support | Details | Remarks |
1 | AEPC | Cash | NRs. 2,000,000.00 | Including VAT |
2 | RERL | Cash | NRs. 900,000.00 | Including VAT |
3 | From NMHDA members | Cash | NRs. 450,000.00 | |
4 | Thapa Engineering, Butwal | Kind | Pelton Turbine set | 37 kW |
5 | Nepal Yantra Shala, Lalitpur | Kind | Cross-flow Turbine set | 10 kW |
6 | Nepal Machine& Structure, Butwal | Kind | Penstock Pipe | |
7 | Oshin Power, Butwal | Kind | Penstock Pipe | |
8 | Universal Equipment, Butwal | Kind | Penstock Pipe | |
9 | Appropriate Engineering, Butwal | Kind | Flange | |
10 | Gautam Energy Industries, Butwal | Kind | Expansion Joint |
The construction of the project was initiated in July 2012 with support of AEPC, RERL and NMHDA members, and aimed to complete within one year. But, due to lack of fund the construction work was stopped for one year and half. The works have been resumed from December 2014 with target to complete in eight months from the restart.
In this phase, NMHDA is putting efforts to complete the remaining tasks such as pipe canal in replacement of the portion damaged by land slide swept portion which is a part of the canal of 37 kW system, forebays of both 37 kW and 10 kW systems, laying of penstock pipes along with support piers and anchor blocks, power house, installation of turbines, generators, ELCs and accessories and construction of tailrace. Construction of power house foundation and forebays had been already done. Likewise, baseframes with tailraces have been installed.
The major portion of the received fund was spent in site clearing, construction of Dam, Desalting basin and headrace Canal. Transportation of construction materials and Hydro-Mechanical components had raised some expenses beyond the estimate.
In observing the estimated cost and current status of the project, 50% of project cost (i.e. NRs. 5,500,000.00) is in deficit to complete the whole construction and installation works as targeted.
But in first stage, we are planning to complete machine foundation, power house construction, penstock pipe laying, forebay construction, internal synchronization of power generated by two different units, transmit and distribute to local consumers. These all will be completed with a fund of NRs. 3,000,000.00 (three million rupees) as per estimates.
NMHDA being a non-profit motive organization have to manage funds from sources like government organizations, international development supporters, international non-government organizations and institutions. NMHDA, the developer of the Model MHP will welcome support for sub-division of packages if an organization/institute or group of organizations/institutes is/are interested. Construction of Powerhouse, Internal synchronization and synchronization to Grid may be options to interested supporter/s to undertake according to the plan.
नेपाल लघु जलविद्युत विकास संस्थाको २५औं वार्षिक साधारण सभा को समापन समारोहमा अध्यक्ष श्री कृष्ण प्रसाद देवकोटाबाट प्रस्तुत स्वागत...
Read more...Nepal Micro Hydropower Development Association (NMHDA) organized its 25th Annual General Meeting on April 12, 2018 which took place...
Read more...President of NMHDA Krishna Prasad Devkota, speaking from the chair said that the private sector now have to...
Read more...Nepal Electricity Authority (NEA) and two micro hydropower plants had entered Power Purchase Agreement (PPA) in late March 2016. Following...
Read more...Nepal had established itself as hydropower pioneer in Asia by successfully commissioning the Pharping Powerhouse in Kathmandu on 22nd...
Read more...For the development of micro hydropower sector, NMHDA had contributed significantly by producing trained manpower as MHP Operators. The...
Read more...